Time to review the project completion deadline as pandemic rages on

By Alice Tan,
Edmund Tie
/ EdgeProp Singapore |
SINGAPORE (EDGEPROP) - The Covid-19 pandemic has accelerated to such an extent that it has now gripped more than 180 countries especially in the US, Europe and the Middle East. Fears of economic and financial fallout from Covid-19 has resulted in steep losses across major stock markets. There were even two rounds of emergency interest rate cuts to near zero by the US Federal Reserve on March 3. That, however, did not stem the stock market rout on March 15. Market sentiment has turned south rapidly as equities and currencies plunged, closely tracking the number of new confirmed cases of Covid-19 that has been escalating daily to about 400,000 globally as at March 25.
Market sentiment has turned south rapidly as equities and currencies plunged (Photo: Albert Chua/EdgeProp Singapore)
Market sentiment has turned south rapidly as equities and currencies plunged (Photo: Albert Chua/EdgeProp Singapore)
Far-reaching and unpredictable, Covid-19 has morphed into the “black swan” event that will continue to derail economic, business and social activities worldwide. An economic recession this year is becoming a possiblity as more countries have declared lockdowns to contain the outbreak. These involve mandatory geographic quarantines, travel bans and recommendations to stay home as well as restrictions on mass social gatherings.
Singapore — being an open economy and similarly imposing travel restrictions on visitors from more countries — will not be spared from the sudden fallout impacting tourism, trade and investment. While the impact is felt immediately by businesses in the tourism, hospitality, retail and other service-oriented sectors, our local construction and real estate industry is facing a daunting challenge — global supply disruptions of construction materials and labour that have impacted construction projects.
Advertisement
These disruptions, if prolonged, would have far-reaching implications with regard to property developers’ ability to meet the five-year project completion period (PCP) for residential projects.

Halts to labour and material supply

Since after the Lunar New Year, construction progress of various property developments in Singapore has been affected by labour and materials disruptions. This was because mainland Chinese workers who returned home were either served Leave of Absence or not allowed to return to Singapore in the near term. Key construction materials — mainly aluminium components, tiles, kitchen carpentry and fittings from mainland China — were not delivered on time as many factories have not reverted to full capacity. As a slight reprieve, mainland China gradually resumed production since mid-March and supply of these materials to Singapore was gradually restored.
To help businesses on manpower crunch during this period, the Ministry of Manpower (MOM) is waiving levies for employers with eligible foreign workers serving quarantine leave of absence or stay home notices. However, it has not done so for all foreign workers, as MOM felt the measures to deal with the short-term fallout should not negate longer-term efforts to encourage companies to restructure and become less reliant on foreign manpower.
To compound woes, greater difficulties now abound for the construction industry as the Covid-19 situation continues. Disruptions to production and supply chains have now widened beyond mainland China to other key production countries in the US, Europe and recently, Malaysia.
Supply disruption of construction materials from Europe — such as marble, tiles, kitchen equipment and other specialist mechanical and electrical equipment and components — added to procurement difficulties for contractors as the pandemic raged across Italy, Germany, France, Spain and the Middle East, after these countries imposed lockdowns since mid-March.
The lockdown imposed by Malaysia that restricted visitors and workers from travelling in and out of the country (Photo: Albert Chua/EdgeProp Singapore)
The lockdown imposed by Malaysia that restricted visitors and workers from travelling in and out of the country (Photo: Albert Chua/EdgeProp Singapore)
The lockdown imposed by Malaysia that restricted visitors and workers from travelling in and out of the country — imposed on March 18 and then extended until April 14 — has created huge inconveniences for many Malaysians working in Singapore, especially in the construction industry. The Singapore government has explored ways to provide accommodation for Malaysian workers who chose to stay in Singapore, and has helped employers with the related costs.
Advertisement
However, it is observed that — at least anecdotally — many others have also stayed in Malaysia, adding labour pressures on various trades dependent on Malaysian workers, such as the construction industry where most Malaysians work as tower crane drivers, heavy machine operators, supervisors and foremen and other specialist tradesmen.
Delays in prefabricated prefinished volumetric construction (PPVC) are a concern due to the requirement of only fully fitted PPVCs being allowed to be installed on site. To ease pressures on PPVC projects affected by delayed supplies of construction materials from mainland China, the Building and Construction Authority (BCA) has allowed 13 ongoing projects (as at March 4) to firstly install partially completed PPVC modules on-site and finish the work when the delayed materials arrive.
Malaysia’s lockdown has also created a fresh disruption in supply of PPVC modules or precast concrete carcasses, with reportedly about 80% of these coming from factories in Johor Baru. According to BCA, there are a total of 44 PPVC projects, of which 35 are private residential and HDB projects, in various stages of progress. Now with even the supply of PPVC modules and various other construction materials (such as cement, precast modules and carpentry) being disrupted in Malaysia, no other work can continue.
Beyond these disruptions, the psychological and operational impact of Covid-19 on the construction workforce with over 340,000 foreign workers could affect their well-being, health and productivity. Many of the foreign workers live in dormitories and are exposed to higher threat of widespread viral outbreak within their confined communities. With news of some foreign workers being infected and new confirmed Covid-19 cases continuing to rise in Singapore, contractors are likely to face greater difficulty to retain and recruit both foreign and local workers.
Invariably, the confluence of these disruptive factors of manpower and material shortage, worker morale, and heightened precautionary measures at dormitories and worksites, will bring about a resultant slowdown in construction progress.
Should the Covid-19 pandemic prolong and lockdowns in Malaysia and other key exporting countries continue, the extended challenges could be beyond the direct control and mitigating measures that contractors can deploy. As such, delays in the construction progress of residential projects in Singapore will be significant, at least for the first half of 2020.
Advertisement
Given such onerous downsides, the main task now is for the authorities to calibrate key measures as soon as it is practicable. The goal here is to save businesses before company survivability in the construction industry deteriorates further.
The lockdown imposed by Malaysia that restricted visitors and workers from travelling in and out of the country (Photo: Albert Chua/EdgeProp Singapore)
Plagued by the disruption difficulties, more contractors are submitting requests for Extension Of Time (EOT) for their construction completions to property developers (Photo: Albert Chua/EdgeProp Singapore)

Difficulty for private developers to support contractors

Plagued by the disruption difficulties, more contractors are submitting requests for Extension Of Time (EOT) for their construction completions to property developers. The authorities have also encouraged developers to take a sympathetic view of construction project delays and grant requests for EOT. However, it would be a difficult call for developers at this stage to grant EOT to the main contractor based on contractual or ex-gratia basis.
There are two considerations that are likely weighing on the minds of developers. First, developers will have to review contractors’ proposed mitigating measures and their substantiation that such measures are insufficient to resolve delays, so as to invoke provisions such as force majeure. However, most standard forms of construction contracts in Singapore do not spell out pandemic as a force majeure event, rendering the contractors’ case for EOT based on Covid-19 difficult. Would developers then grant EOT on an ex-gratia basis?
Secondly, despite the clear issues of supply disruptions and construction delays, the five-year Project Completion Period (PCP) deadline imposed on developers is a key deterrent for most of them to grant EOT to contractors. Currently, developers must build and sell all units in a residential project within five years from the time of land acquisition, failing which, the remission of Additional Buyer’s Stamp Duty (ABSD) will not be granted, and developers have to pay ABSD of 15% and 25% of the land price plus interest, for sites acquired before July 6 2018, and on/after, respectively. As such, developers must adhere to the project completion and sell-out timelines strictly within five years to avoid the ABSD payment. This timeline is becoming a compressed issue for all players in the construction and real estate supply chain.
The downstream impact arising from non-EOT being granted to contractors would add further hardships to contractors as many continue to incur overhead costs even if their projects are partially stopped. Developers, too, face cash flow disruptions as they are not able to draw-down progress payments from financial institutions arising from construction delays. Adding to their cash flow constraints, contractors are likely to face difficulty in collection progress payments from their developer clients as the slowdown progresses. These immediate financing issues — coupled with the subsequent “bunching up’’ of resource crunch and higher construction costs at the later stages of construction to keep up with timelines — could impact quality deliverables, which do not bode well for the industry and homebuyers.
Beyond the interests to deliver completed properties in time for homebuyers, the interest of the stakeholders (contractors, suppliers and developers for example) — especially in this unprecedented time of Covid-19 outbreak — needs to be closely considered by the authorities. The hardship that is to come for the construction and real estate industry could be greater than initially envisaged, as the global economy is forecast to worsen with various industries hard-hit by the pandemic and job losses are inevitable.
Demand for private homes could wane as a result, putting greater pressures on developers. With the prevailing unsold inventory of more than 30,000 private homes and assuming 9,000 new homes could still be sold annually, it could take more than three years from now (that is, beyond 2023), to absorb this inventory. Therefore, some developers who bought land during the 2017 and 2018 period may either narrowly meet or miss the five-year PCP deadline in the event that demand weakens.
Taking into consideration this multitude of pandemic-induced issues plaguing the construction and real estate industry, a pre-emptive approach towards the prevailing five-year PCP measures imposed on developers need to be introduced. In November 1997, the PCP for residential projects was extended from four to five years to eight years due to the fallout from the Asian Financial Crisis. PCP was later cut to six years in 1999.
In Budget 2009, the government allowed developers to apply for extension of PCP by up to one year for private residential projects without having to pay an extension premium. From Aug 5 2010, the PCP was cut from six years to five years for all government land sale sites, due to shortage of supply then and to ensure there were adequate homes.
Currently, this threat of home shortage has diminished, and with the fallout caused by Covid-19 becoming a bigger concern, it is time to consider calibrating PCP back to six years.
A case-by-case basis approach, during this time of growing pressing issues for the industry, is less effective since time is required to review each case, and contractors in the meantime will continue to suffer.
The PCP measure needs to be calibrated to apply for all residential projects. This will speed up implementation and conserve administrative resources while cushioning the construction and real estate industry from further hardships.
Alice Tan is the Senior Director of Research & Consulting at Edmund Tie
Read also:

Follow Us
Follow our channels to receive property news updates 24/7 round the clock.
EdgeProp Telegram
EdgeProp Facebook
Subscribe to our newsletter

Our Site

Edgeprop.sg (previously known as The Edge Property Singapore) is the best property portal for real estate agents, investors, home-seekers and sellers alike in Singapore. On EdgeProp, you will be able to find the latest and hottest property news, property listings, and access tools for your research and analysis.

Whether you are looking to buy, sell or rent apartments, condominiums, executive condos, HDBs, landed houses, commercial properties or industrial properties, we bring you Singapore’s most comprehensive and up-to-date property news and thousands of listings to facilitate your property decisions. Click into any listing to check out the new AI Redesign tool to envision your property based on your preferred style, be it Scandinavian, Minimalist or many others.

View More