[UPDATE] Tackling challenges faced by Covid-hit construction sector
By Timothy Tay
/ EdgeProp Singapore |
SINGAPORE (EDGEPROP) - Lego-style modular construction or prefabricated prefinished volumetric construction (PPVC) was intended to wean Singapore’s construction sector from its dependence on a foreign workforce. It is faster, more efficient and environmentally friendly compared to conventional construction. (See also: Covid-19 catalyses digitalisation in construction)
However, even PPVC specialists have not been spared the ravages of the Covid pandemic. They have been just as affected by the travel ban on long-term pass holders from India and Bangladesh due to a surge in Covid infections. This immediately cut off the supply of construction workers from the two main source countries.
“Based on my experience, the construction industry is facing a 20%-30% shortage in foreign manpower, and the situation is aggravated by the tighter border controls,” says Khor Yew Chai, director (PPVC) at Dragages Singapore, a member of Bouygues Constrution, a global leader in the building sector.
Advertisement
Under the PPVC method, frameworks and modules are built in a factory off-site. “We still need workers in these factories to produce the modules,” adds Khor. “The difference is that with PPVC, we do not require as many workers onsite compared to a conventional construction site.”
Dragages’ modules are built in a factory located in Johor, Malaysia, before being transported to a factory in Singapore to be assembled. However, most of the construction materials are imported from overseas, especially China, notes Khor. “The rise in costs of sea transport and raw materials since last year is a challenge for contractors trying to complete their projects on schedule,” he adds.
Dragages is not alone. Many of the precast components are manufactured in Malaysia, notes Tan Cheng Chuah, managing director of Construction Professionals and PM Link, two companies under CPG Corp, a professional development consultancy firm.
Malaysia entered a 14-day Covid “total lockdown” with effect from June 1 to contain its daily infections. It has since been extended by another two weeks to June 28. “The initial Movement Control Order and the current Full Movement Control Order have impacted the completion timelines for ongoing projects in Singapore as precast factories in Malaysia have to stop production and deliveries,” continues Tan. “The result is that overall tender prices for construction projects have escalated by 20%-30% over the past year.”
Double-blow
Productivity at construction sites has dropped due to the safe management measures (SMM) introduced as part of the Phase Two (Heightened Alert) measures put in place from May 16 to June 13.
The government is aware of the manpower shortage and subsequent knock-on effects on ongoing infrastructure and development projects. In a speech at the OrangeTee Business Conference on May 24, the Minister for National Development, Desmond Lee, said: “[The tighter border controls] has significantly worsened manpower shortages in our construction sector, as South Asian countries are where we recruit and hire most of our construction work permit holders.”
Advertisement
This is a double-blow for the construction industry, which had already been struggling with a manpower crunch since the start of the pandemic last year. “We have been cautious in reopening our borders and have also been careful in bringing in migrant workers, to reduce the risk of importing the virus,” adds Lee. “It’s a difficult trade-off.”
Last year, the government introduced a $1.36 billion construction support package to help contractors bear part of the additional costs they had to incur due to construction delays and SMM.
The government has stepped in with more support measures, including an additional 49-day extension for public-sector construction projects on top of the 122-day extension under the Covid-19 (Temporary Measures) Act, or Cotma, last year. Contractors who have been awarded contract sums of up to $100 million will receive 0.1% of the awarded contract sum for every month of delay as payment for non-manpower-related qualifying costs under Cotma.
Foreign worker levy rebates for work permit holders will be increased from $90 per worker per month to $250 per worker per month, from May to December 2021.
Co-sharing of increased manpower costs
To alleviate the manpower crunch, the government will temporarily allow new construction work-permit holders from China to enter Singapore to work first and take their skills certification tests locally instead of in China.
“Governmental support measures such as the Jobs Support Scheme helped to a certain extent as they covered about 15%-20% of manpower cost. In addition, the ex-gratia payment from the government for supporting material and equipment [purchases] also helped contractors,” says Chuck Kho, deputy CEO of CPG Consultants, which is part of CPG Corp.
Advertisement
A Cotma law has been amended to allow construction companies in Singapore to apply to the authorities for adjustments to contract sums so that project partners will more equitably share the burden of increased foreign manpower costs due to the Covid pandemic. “This is to ensure no single stakeholder group in the construction industry bears an undue share of the burden imposed by Covid-19,” said Minister Lee in Parliament on May 11.
“The co-sharing mechanisms involve some documentation process and substantiation of the qualifying costs,” says Dragages’ Khor. “The catch is that all parties involved — contractors, including subcontractors and suppliers — must have the same objective of sharing the cost.”
Dragages has six ongoing projects in Singapore, and is focused on completing four of them by the end of the year, for instance, the 613-unit condominium project, The Garden Residence; the 805-unit condominium, Park Colonial; and the Grade-A office development, CapitaSpring.
Project delays
Most ongoing construction projects in Singapore however, are facing delays of between six and 12 months, says CPG Consultants’ Kho. Further delays are likely, he cautions, “as overlapping problems cause a ripple effect across the industry”.
For instance, some of CPG Consultants’ clients have preferred to delay tenders due to concerns over funding, cost escalations, labour shortage, and the prolonged environment of heightened risk and uncertainty, says Kho.
For firms engaged in the built environment, the main cost component in project prolongation is inevitably manpower, notes Tan of Construction Professionals. Besides more measures on manpower cost-sharing, another way to alleviate the rise in manpower costs is for a more flexible procurement method to cushion the uncertainty due to Covid, he adds.
Instead of an all-cost-inclusive construction tender or consultancy tender, for example, public agencies may consider including a provisional sum for costs that cannot be estimated or foreseeable in the short term, such as the costs of swab tests, prolongation costs, and the costs of implementation of mandatory SMM, Tan suggests.
The Covid-related construction delays is taking a toll on the finances of developers and contractors. “If these delays are prolonged, it is likely that some of the smaller developers may face serious cashflow issues,” warns Chia Ngiang Hong, president of the Real Estate Developers’ Association of Singapore (Redas).
Extension of ABSD remission period
One issue that most, if not all, developers are concerned about is the additional buyer’s stamp duty (ABSD). Since the July 2018 property cooling measures, developers are subjected to a 30% ABSD, of which 5% is non-remittable.
Developers were given a 12-month extension to the five-year project completion period last year, as part of Cotma. However, the ABSD period was only extended by six months, to 5.5 years.
Most of the government assistance to the industry, including the reprieve to the completion deadline, was handed out close to the onset of the pandemic last year, says Redas’ Chia. “If developers continue to face the threat of having to pay heavy penalties with regard to the ABSD on land cost, they will likely adopt a more conservative attitude when negotiating with contractors,” he adds.
An extension of the developers’ ABSD period will provide relief from “the time pressure” that developers and their contractors face, continues Chia.
Local pool of skilled workers
“The reality is that there is no easy solution while most Singaporeans are not inclined to switch to manual labour professions, whether skilled or not,” says CPG Consultants’ Kho.
Despite rapid technological advancements taking place in the construction sector, robotics and automation cannot completely displace workers — “at least not in the next 10 years”, says Construction Professionals’ Tan.
One option to solve the foreign worker crunch is to train a pool of local skilled workers to reduce the reliance on foreign labour, adds Tan. Adequate training and remuneration should be sufficient to entice local skilled construction workers to enter and stay in the industry, he argues. “This should go hand in hand with the widespread adoption of PPVC technology and digitalisation as a long-term solution for Singapore’s built environment.”
Check out the latest listings near The Garden Residence, Park Colonial
https://www.edgeprop.sg/property-news/tackling-challenges-faced-covid-hit-construction-sector
Follow Us
Follow our channels to receive property news updates 24/7 round the clock.